Construction File: Risks to Owners of In House Construction When Projects are Over Budget
If the lowest compliant bid exceeds the Owner's budgeted amount, and the Owner is unwilling or unable to award a contract at the bid price but is unwilling to abandon the project, the following guidelines for a course of action are recommended:
- Where the amount by which the bid price must be reduced is less than 15% of the lowest compliant bid, the first step should be to negotiate with the lowest compliant bidder (only) to identify changes in the scope or quality of the work and a corresponding bid price reduction. Where the Owner and lowest compliant bidder can agree on acceptable changes and a corresponding bid price reduction, the changes should be documented as a post-bid addendum and the contract, based on the negotiated reduced price, should be awarded to the lowest compliant bidder. However, where acceptable changes and a corresponding bid price reduction cannot be successfully negotiated with the lowest compliant bidder, the second step should be to re-bid on modified Bid Documents under a new bid call. Negotiations should be limited exclusively to the lowest compliant bidder.
- Where the amount by which the bid price must be reduced exceeds 15% of the lowest compliant bid, the bidcalling authority may immediately undertake either of the preceding steps described above, at its discretion. That is, the Owner may negotiate with the lowest compliant bidder first to re-bid on modified Bid Documents without any attempt to negotiate.
Re-bidding should be avoided whenever possible because of the additional time and costs incurred by all parties. Where a re-bid is unavoidable, the Bid Documents should be sufficiently modified to achieve a reduced bid price that will be acceptable to the Owner.
A standard 'privilege clause' in the bidding requirements would give the Owner the right to not accept any bid, thereby permitting the Owner to either abandon the project or reject all bids, and subsequently invite a re-bid on modified Bid Documents under a new bid call. However, since it is recommended that the Owner negotiate with the lowest compliant bidder in some circumstances, it is important that the bidding requirements include a clause giving the Owner, if necessary, the right to negotiate a reduced price with the lowest compliant bidder.
The risks for Owners to convert to in house forces when a project is over budget are:
- The trade prices received by the prime contractor are proprietary to that prime.
- When the Owner takes on this role they become a NON preferred Owner by the industry. Future projects will be viewed in a different light. See Construction File of January 2006, Maximizing the Competitive Bid.
- The Owner may not be addressing the same General Conditions of the prime contract as the prime contractor.
- Is it really under budget when the final price comes in i.e. all direct costs and overhead accounted for?
- A change in contracting structure will impact the relationship with the consultants and may result in increased fees.
- The Owner loses the benefit of a fixed price contract and now has to absorb labour and material escalation.
- The Owner must have in-house expertise to evaluate tenders and procedures.
- Does the Owner understand Division 1 requirements i.e. safety, insurance, contract security, shop drawing review, maintenance manuals?
- The value of the Superintendent is negated; who does the on-site coordination, job scheduling, project management, material procurement etc?
- Owner now has safety responsibilities as Prime Contractor of a multiple employer worksite. If an accident occurs it may impact WCB rates and may move the Owner from one class of WCB rates i.e. supervisory staff to construction rates.
- Owner is now responsible for regular quality control expertise, coordinating and administering latent defects, and warranty costs.
- Owner is now taking on the prime contractors risk with respect to trade contractor failure. This risk now carries upwards in the Owner's governing structure i.e. to a Board of Directors.
- The Owner assumes the insurance and bonding responsibilities which should be maintained for the project.
Receiving Bids Efficiently in the 21st Century
Construction File: BCCA’s position on the BC NDP's Community Benefits Agreement
Construction File: What the New National Trade Agreements Mean to You
Construction File: Introducing the BCCA Guideline to Construction Close-Out Procedures
Construction File: Pre-qualification of Contractors
Construction File: Proactive Release of Project Information for the Construction Industry
Construction File: The Construction Management Project Delivery Method
Construction File: Public Openings for Online Bidding
Construction File: CCA Quality of Documents Report Issued
Construction File: Onerous Bidding Conditions in 2015
Construction File: Top 10 Reasons BidCentral’s Online Bidding is a Home Run
Construction File: Job Order Contracting
Construction File: Liquidated Damages Clauses
Construction File: The Importance of Planholder Lists
Construction File: Post Closing Over Budget Negotiations
Construction File: The Pitfalls of Incomplete Contract Documents
Construction File: BidCentral - By the Industry for the Industry
Construction File: What is Fair, Open and Transparent Bidding?
Construction File: Trade Contractors in Post Bid Negotiations and Trade Agreements
Construction File: Prompt Payment Creates a Sustainable Industry
Construction File: Fair Markups on Changes to the Work
Construction File: Tercon Decision Important for Construction Industry
Construction File: BCDC Standard Documents and Guidelines for a Stipulated Price Bid
Construction File: BidCentral implements new e-bonding
Construction File: Aboriginal Business Enhancement and Set-Aside Programs
Construction File: Liquidated Damages Clause
Construction File: BCCA Introduces a Guideline for Choosing a Project Delivery Method
Construction File: BCCA’s External Policy for Use of Owner Forces on Public Funded
Construction File: Onerous Bidding Conditions Continue to Trouble Industry
Construction File: Outsourcing = Best Value
Construction File: The Importance of Providing Bid Results
Construction File: Tercon Decision Important for Construction Industry
Construction File: Trade Contractors in Post Bid Negotiations and Trade Agreements
Construction File: The Cost of Onerous Bidding Conditions
Construction File: BCCA introduces the Electronic Bidding System
Construction File: Liquidated Damages Clause
Construction File: Maximizing Competitive Bidding 2009
Construction File: Pre-qualification Contributes to the Rising Cost of Construction
Construction File: Publicly Funded Building Projects - Standard Stipulated Price Contract Documents Updated
Construction File: Use of Standard Documents Reduces Risks
Construction File: Use of Standard Documents Reduces Risks
Construction File: CCDC issues new CCDC2 Stipulated Price Contract
Construction File: Risks to Owners of In House Construction When Projects are Over Budget
Construction File: A Guide to Standards & Practices in the Construction Industry
Construction File: BC Government Introduces Capital Procurement Audit Tool for Capital Asset Management Framework
Construction File: The Importance of Planholder List
Construction File: BCCA to Issue Onerous Bidding Alerts
Construction File: Myths of Gold Seal Requirements as a Condition of Contract
Construction File: Completion of Projects - Getting the Deficiencies Done!
Construction File: Why The Public Construction Council of BC?
Construction File: Procuring Trade Contractor Bids
Construction File: Pre-qualification of General Contractors and Trade Contractors
Construction File: Pre-qualification of General Contractors and Trade Contractors
Construction File: Maximizing Competitive Bidding
Construction File: Construction Management - Selection of CM and Contractor Services
Construction File: A Summary Guide for BC Construction Industry Standards and Guidelines
Construction File: BCCA Policy Gold Seal as a Condition of Contract
Construction File: BCCA POLICY FOR THRESHOLDS FOR PROCUREMENT OF PUBLICLY FUNDED CONSTRUCTION
Construction File: A Guide to the Use of Cash Allowances
Alternative Prices – Should They Be Used and How to Use Them Effectively
Publicly Funded Building Projects - Standard Stipulated Price Contract Documents Now Available Online
Construction File: Keeping Projects on Budget and Over Budget Negotiations
Construction File: COOLNet meets the requirements of AIT
Construction File: HOW DO YOU FIND THE RIGHT TRADE CONTRACTORS FOR YOUR PROJECT?
Construction File: Addressing Holdbacks
Construction File: Dangers of Owner-Supplied Equipment
Construction File: Standard Documents Provide Good Value