Construction File: Introducing the BCCA Guideline to Construction Close-Out Procedures
Download the PDF Version here.
BCCA has published a guidelines document “Procedures Concerning Construction Contracts and Close Out of Projects”, modelled after similar reference documents that have existed for some time in Ontario and Alberta.
Getting a construction project to the milestones of Substantial Performance of the Work and then to Completion and Turn Over are some of the most difficult challenges during the construction of a facility. The process involves thousands of actions performed by hundreds, if not thousands, of individuals from all facets of the construction chain including manufacturers, distributors, suppliers, subcontractors, sub-subcontractors, contractors, construction managers, consultants, allied professionals, project managers, developers, owners, government, and end users. While the obligations of each are often detailed in the project documents (The BCCA Guideline follows those of a CCDC Contract), they are not always coordinated as well as they could be, which can lead to costly delays in achieving Substantial Performance and then Total Completion.
If End Users are not able to use the facility as intended, completion will take more time and money and result in delay of payments. The BCCA Guideline has been created to help the project closeout go more smoothly: often, the last 3% of the project is often taking at least 15% of the effort. It takes a collaborative effort to make sure the last 3% of the project consumes 3% or less of the effort.
The BCCA Guideline has been produced by the BCCA’s Standards and Practices Committee. Its primary purpose is to introduce best practices which will expedite and simplify the takeover of a project by its owner from the contractor who managed its construction. The Guideline includes recommended practices following the principles and methods for successfully completing the takeover process efficiently for all parties.
The BCCA Guideline was prepared in response to members of the construction industry reporting that the closing out of construction projects was becoming increasingly difficult. Several key problem areas were identified:
- Timeliness – Takeover issues need to be addressed before the tendering of the project. For example the owner / consultant should communicate expectations in the bid documents, and then address them from the first site meeting onward and at every subsequent site meeting.
- Communication – The owner / consultant needs to communicate the quality standards on a particular project within the specifications at the time of the bidding process, and include the specific requirements in regard to deliverables and the level of commissioning activities to be completed prior to owner’s occupancy. The communication must be continued throughout the project (there should be no surprises toward the end of the project).
- Teamwork – Something as complex and expensive as a construction project is best built with a sense of teamwork. If everyone in the process approaches the project with the sense that they are there to provide a quality job on time and on budget in a spirit of cooperation, a project can and will go very well. The subcontractors and suppliers should be expected to be active participants in the project and take responsibility for the quality and scheduling of their work, work cooperatively with the contractor, consultants and other subcontractors, be mindful of the construction schedule and attend to deficiencies as soon as they come to their attention.
The recommendations in the BCCA Procedures Concerning Construction Contracts and Close Out of Projects reflect these ideas and more. It is in the interests of the whole construction industry - including owners -- to make the takeover of construction projects more time effective and less stressful for all participants.
.jpg)
.jpg)
Receiving Bids Efficiently in the 21st Century
.jpg)
Construction File: BCCA’s position on the BC NDP's Community Benefits Agreement
.jpg)
Construction File: What the New National Trade Agreements Mean to You
.jpg)
Construction File: Introducing the BCCA Guideline to Construction Close-Out Procedures
.jpg)
Construction File: Pre-qualification of Contractors

Construction File: Proactive Release of Project Information for the Construction Industry

Construction File: The Construction Management Project Delivery Method

Construction File: Public Openings for Online Bidding

Construction File: CCA Quality of Documents Report Issued

Construction File: Onerous Bidding Conditions in 2015

Construction File: Top 10 Reasons BidCentral’s Online Bidding is a Home Run

Construction File: Job Order Contracting

Construction File: Liquidated Damages Clauses

Construction File: The Importance of Planholder Lists

Construction File: Post Closing Over Budget Negotiations

Construction File: The Pitfalls of Incomplete Contract Documents

Construction File: BidCentral - By the Industry for the Industry

Construction File: What is Fair, Open and Transparent Bidding?

Construction File: Trade Contractors in Post Bid Negotiations and Trade Agreements

Construction File: Prompt Payment Creates a Sustainable Industry

Construction File: Fair Markups on Changes to the Work

Construction File: Tercon Decision Important for Construction Industry

Construction File: BCDC Standard Documents and Guidelines for a Stipulated Price Bid

Construction File: BidCentral implements new e-bonding

Construction File: Aboriginal Business Enhancement and Set-Aside Programs

Construction File: Liquidated Damages Clause

Construction File: BCCA Introduces a Guideline for Choosing a Project Delivery Method

Construction File: BCCA’s External Policy for Use of Owner Forces on Public Funded

Construction File: Onerous Bidding Conditions Continue to Trouble Industry

Construction File: Outsourcing = Best Value

Construction File: The Importance of Providing Bid Results
Construction File: Tercon Decision Important for Construction Industry
Construction File: Trade Contractors in Post Bid Negotiations and Trade Agreements
Construction File: The Cost of Onerous Bidding Conditions
Construction File: BCCA introduces the Electronic Bidding System
Construction File: Liquidated Damages Clause
Construction File: Maximizing Competitive Bidding 2009
Construction File: Pre-qualification Contributes to the Rising Cost of Construction
Construction File: Publicly Funded Building Projects - Standard Stipulated Price Contract Documents Updated
Construction File: Use of Standard Documents Reduces Risks
Construction File: Use of Standard Documents Reduces Risks
Construction File: CCDC issues new CCDC2 Stipulated Price Contract
Construction File: Risks to Owners of In House Construction When Projects are Over Budget
Construction File: A Guide to Standards & Practices in the Construction Industry
Construction File: BC Government Introduces Capital Procurement Audit Tool for Capital Asset Management Framework
Construction File: The Importance of Planholder List
Construction File: BCCA to Issue Onerous Bidding Alerts
Construction File: Myths of Gold Seal Requirements as a Condition of Contract
Construction File: Completion of Projects - Getting the Deficiencies Done!
Construction File: Why The Public Construction Council of BC?
Construction File: Procuring Trade Contractor Bids
Construction File: Pre-qualification of General Contractors and Trade Contractors
Construction File: Pre-qualification of General Contractors and Trade Contractors
Construction File: Maximizing Competitive Bidding
Construction File: Construction Management - Selection of CM and Contractor Services
Construction File: A Summary Guide for BC Construction Industry Standards and Guidelines
Construction File: BCCA Policy Gold Seal as a Condition of Contract
Construction File: BCCA POLICY FOR THRESHOLDS FOR PROCUREMENT OF PUBLICLY FUNDED CONSTRUCTION
Construction File: A Guide to the Use of Cash Allowances
Alternative Prices – Should They Be Used and How to Use Them Effectively
Publicly Funded Building Projects - Standard Stipulated Price Contract Documents Now Available Online
Construction File: Keeping Projects on Budget and Over Budget Negotiations
Construction File: COOLNet meets the requirements of AIT
Construction File: HOW DO YOU FIND THE RIGHT TRADE CONTRACTORS FOR YOUR PROJECT?
Construction File: Addressing Holdbacks
Construction File: Dangers of Owner-Supplied Equipment
Construction File: Standard Documents Provide Good Value