Construction File: Use of Standard Documents Reduces Risks
When documents contain clauses that discourage contractors from bidding, raise the costs associated with bidding, add onerous risk, or limit the competition to a select few bidders, it may come at a cost to the owner. Such an outcome creates the potential for unfairness or misuse of public funds.
Quality construction depends on quality contracts, so we must work together to ensure that the proper standards are adhered to by all—not just in the construction of the project, but also in the construction of the project documents. Standard construction document conditions generally limit the risks of the contractor to those, which can be reasonably foreseen by an experienced and competent contractor. Such risks would include compliance with regulations; construction defects; sub contractor/supplier mistakes; completion dates; and labour and materials issues.
Often the contractor is asked to take on additional risks, and the bid price could be inflated to reflect these risks. Care must be taken not to accept or impose such risks indiscriminately. Inappropriate allocation might simply result in no allocation at all.
Proper allocation of risk is essential in all contractual relations. In the private sector, it is primarily the business of those parties who are signatory to the contract documents. It is assumed that such parties are operating on an even playing field, and therefore must accept or refuse risk as they see fit. With public construction, however, there is more at stake. Public agencies are expected to operate in a fair, accountable and transparent manner. It is in the public’s best interests that unnecessary litigation is avoided, and that risk is dealt with in such a manner as will best protect the public.
Using well-established industry standards when preparing construction documents will mean that those very contractors and trade contractors you wish to attract as bidders will continue to be interested in bidding.
Using Standard Document approved by the Canadian Construction Documents Committee (CCDC) or Canadian Construction Association provides:
- A fair allocation of risk
- Clarity of obligations
- Responsibilities acceptable to all parties
The use of standard documents results in:
- Fewer disputes
- Fewer delays
- Reduction in the cost associated with drafting, implementing and bidding on projects with new contracts
There are industry accepted standard contracts such as the CCDC-2 that provide a balanced approach to risk allocation. We recommend the use of such standard documents. They have been expertly developed by industry in consultation with other stakeholders, including owners (4 representatives), design professionals (7 representatives), and contractors (4 representatives). Consequently, the documents provisions for risk management are appropriate and equitable.
For information on standard documents and industry standards refer to ‘A Summary Guide for BC Construction Industry Standards and Guidelines’ on the BCCA website at: http://bccassn.xpr.cloud/pdfs/Summary_Standard_%20Docs_Guides.pdf
Note: Standard document development is supported by the funds generated from the sales of these documents. Hence, it is in the industries best interest to ensure that any standard documents comply with the copyright requirements of the sponsoring organization.
.jpg)
.jpg)
Receiving Bids Efficiently in the 21st Century
.jpg)
Construction File: BCCA’s position on the BC NDP's Community Benefits Agreement
.jpg)
Construction File: What the New National Trade Agreements Mean to You
.jpg)
Construction File: Introducing the BCCA Guideline to Construction Close-Out Procedures
.jpg)
Construction File: Pre-qualification of Contractors

Construction File: Proactive Release of Project Information for the Construction Industry

Construction File: The Construction Management Project Delivery Method

Construction File: Public Openings for Online Bidding

Construction File: CCA Quality of Documents Report Issued

Construction File: Onerous Bidding Conditions in 2015

Construction File: Top 10 Reasons BidCentral’s Online Bidding is a Home Run

Construction File: Job Order Contracting

Construction File: Liquidated Damages Clauses

Construction File: The Importance of Planholder Lists

Construction File: Post Closing Over Budget Negotiations

Construction File: The Pitfalls of Incomplete Contract Documents

Construction File: BidCentral - By the Industry for the Industry

Construction File: What is Fair, Open and Transparent Bidding?

Construction File: Trade Contractors in Post Bid Negotiations and Trade Agreements

Construction File: Prompt Payment Creates a Sustainable Industry

Construction File: Fair Markups on Changes to the Work

Construction File: Tercon Decision Important for Construction Industry

Construction File: BCDC Standard Documents and Guidelines for a Stipulated Price Bid

Construction File: BidCentral implements new e-bonding

Construction File: Aboriginal Business Enhancement and Set-Aside Programs

Construction File: Liquidated Damages Clause

Construction File: BCCA Introduces a Guideline for Choosing a Project Delivery Method

Construction File: BCCA’s External Policy for Use of Owner Forces on Public Funded

Construction File: Onerous Bidding Conditions Continue to Trouble Industry

Construction File: Outsourcing = Best Value

Construction File: The Importance of Providing Bid Results
Construction File: Tercon Decision Important for Construction Industry
Construction File: Trade Contractors in Post Bid Negotiations and Trade Agreements
Construction File: The Cost of Onerous Bidding Conditions
Construction File: BCCA introduces the Electronic Bidding System
Construction File: Liquidated Damages Clause
Construction File: Maximizing Competitive Bidding 2009
Construction File: Pre-qualification Contributes to the Rising Cost of Construction
Construction File: Publicly Funded Building Projects - Standard Stipulated Price Contract Documents Updated
Construction File: Use of Standard Documents Reduces Risks
Construction File: Use of Standard Documents Reduces Risks
Construction File: CCDC issues new CCDC2 Stipulated Price Contract
Construction File: Risks to Owners of In House Construction When Projects are Over Budget
Construction File: A Guide to Standards & Practices in the Construction Industry
Construction File: BC Government Introduces Capital Procurement Audit Tool for Capital Asset Management Framework
Construction File: The Importance of Planholder List
Construction File: BCCA to Issue Onerous Bidding Alerts
Construction File: Myths of Gold Seal Requirements as a Condition of Contract
Construction File: Completion of Projects - Getting the Deficiencies Done!
Construction File: Why The Public Construction Council of BC?
Construction File: Procuring Trade Contractor Bids
Construction File: Pre-qualification of General Contractors and Trade Contractors
Construction File: Pre-qualification of General Contractors and Trade Contractors
Construction File: Maximizing Competitive Bidding
Construction File: Construction Management - Selection of CM and Contractor Services
Construction File: A Summary Guide for BC Construction Industry Standards and Guidelines
Construction File: BCCA Policy Gold Seal as a Condition of Contract
Construction File: BCCA POLICY FOR THRESHOLDS FOR PROCUREMENT OF PUBLICLY FUNDED CONSTRUCTION
Construction File: A Guide to the Use of Cash Allowances
Alternative Prices – Should They Be Used and How to Use Them Effectively
Publicly Funded Building Projects - Standard Stipulated Price Contract Documents Now Available Online
Construction File: Keeping Projects on Budget and Over Budget Negotiations
Construction File: COOLNet meets the requirements of AIT
Construction File: HOW DO YOU FIND THE RIGHT TRADE CONTRACTORS FOR YOUR PROJECT?
Construction File: Addressing Holdbacks
Construction File: Dangers of Owner-Supplied Equipment
Construction File: Standard Documents Provide Good Value