Construction File: Fair Markups on Changes to the Work
Download the PDF Version
The impact of changes in the scope of work – both time and money – is probably the single most disputed issue in construction. Therefore, in order to keep the project moving toward completion, the contractual provisions governing changes must be fair as well as effective in encouraging the timely resolution of cost and time issues.
However, feedback from contractors is that change order markups are a major issue. Two decades ago, the discussion about markups on changes to the work was not as intense as it is today. What has changed?
Although incomplete drawings and specs are not the sole cause for there being changes on construction projects, contractors today estimate that 20-30% of their end contract is comprised of change orders for that reason. This is borne out in reports provided by independent consultants as identified in our previous Construction File on the Pitfalls of Incomplete Contract Documents.
When providing a price, contractors expect that the contract documents are complete and accurately reflect the project requirements, and that any changes, errors or omissions will lead to a change order with commensurate adjustment to both the contract price and project duration. The competitive environment means contractors and their subcontractors are understandably reluctant to add allowances to their tendered price, recognizing that adding any costs increase the risk that they will not be low bidder.
Complete contract documents are the responsibility of the owners, but the contractors are often negatively impacted by a lack of adequate mark-ups on changes to the work specified in Contract Documents. In some cases, the specified artificially-low mark-ups do not even cover the cost of putting together change order pricing. Also, keep in mind that when changes do not proceed, the contractors receive no compensation for work done to price the proposed change.
Contractors are sometimes seen as being aggressive in the pursuit of change orders, while the reality is most contractors would much prefer not to have any.
What are fair mark ups on changes to the work?
In discussions with Owners, Design Professionals and Contractors through the BC Documents Committee, BCCA has agreed in BCDC 2, 2013 on the following as a Supplementary Condition to CCDC 2, 2008; GC 6.2 Change Order, add a clause 6.2.3:
The following shall determine Contactor markup on Change Orders by percentage:
- To the cost of the Work performed by the Contractor directly, the Contractormay add a maximum of 20% markup for overhead and profit combined.
- To the cost of the Work performed by Subcontractors for the Contractor, before the Subcontractor’s markup, the Contractor may add a maximum of 10% markup for overhead and profit combined.
- On Work deleted from the Contract, not covered by unit prices, the credit to the Owner shall be the cost of the Work as set out in GC 6.3 – CHANGE DIRECTIVE, article 6.3.7.
- For a detailed list of what the Contractor may include in the cost of the work before adding markups, refer to GC 6.3 CHANGE DIRECTIVE, article 6.3.7.
How are Subcontractor and Supplier mark-ups determined?
CCDC 2, 2008, GC 3.7.1.2 says that ‘the Contractor shall incorporate the terms and conditions of the Contract Documents into all contracts and written agreements with Subcontractors and Suppliers’. Hence, the Subcontractors and Suppliers would merit the same markups as noted above.
It is unreasonable to assume that a contractor can survive at a low markup. As the market continues to evolve, the contractors will evaluate the state of the tender documents, the owner history and Supplementary General Conditions (in particular markups on changes to the work) and may opt not to bid, or to bid with margins that include contingencies to ensure profitability.
The result may be inflated bids intended to minimize risk, resulting in contract prices which will not benefit an owner. Hence, unfair bidding conditions such as unreasonable markups are not in the best interest of the tax payers. Implementing fair practices for changes to the work is sound policy.
![construction-file-default(1).jpg](/media/400x300/construction-file-default(1).jpg)
![construction-file-default(1).jpg](/media/400x300/construction-file-default(1).jpg)
Receiving Bids Efficiently in the 21st Century
![construction-file-default(1).jpg](/media/400x300/construction-file-default(1).jpg)
Construction File: BCCA’s position on the BC NDP's Community Benefits Agreement
![construction-file-default(1).jpg](/media/400x300/construction-file-default(1).jpg)
Construction File: What the New National Trade Agreements Mean to You
![construction-file-default(1).jpg](/media/400x300/construction-file-default(1).jpg)
Construction File: Introducing the BCCA Guideline to Construction Close-Out Procedures
![construction-file-default(1).jpg](/media/400x300/construction-file-default(1).jpg)
Construction File: Pre-qualification of Contractors
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: Proactive Release of Project Information for the Construction Industry
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: The Construction Management Project Delivery Method
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: Public Openings for Online Bidding
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: CCA Quality of Documents Report Issued
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: Onerous Bidding Conditions in 2015
![construction-file-top-10.png](/media/400x300/construction-file-top-10.png)
Construction File: Top 10 Reasons BidCentral’s Online Bidding is a Home Run
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: Job Order Contracting
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: Liquidated Damages Clauses
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: The Importance of Planholder Lists
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: Post Closing Over Budget Negotiations
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: The Pitfalls of Incomplete Contract Documents
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: BidCentral - By the Industry for the Industry
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: What is Fair, Open and Transparent Bidding?
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: Trade Contractors in Post Bid Negotiations and Trade Agreements
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: Prompt Payment Creates a Sustainable Industry
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: Fair Markups on Changes to the Work
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: Tercon Decision Important for Construction Industry
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: BCDC Standard Documents and Guidelines for a Stipulated Price Bid
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: BidCentral implements new e-bonding
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: Aboriginal Business Enhancement and Set-Aside Programs
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: Liquidated Damages Clause
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: BCCA Introduces a Guideline for Choosing a Project Delivery Method
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: BCCA’s External Policy for Use of Owner Forces on Public Funded
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: Onerous Bidding Conditions Continue to Trouble Industry
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: Outsourcing = Best Value
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)
Construction File: The Importance of Providing Bid Results
Construction File: Tercon Decision Important for Construction Industry
Construction File: Trade Contractors in Post Bid Negotiations and Trade Agreements
Construction File: The Cost of Onerous Bidding Conditions
Construction File: BCCA introduces the Electronic Bidding System
Construction File: Liquidated Damages Clause
Construction File: Maximizing Competitive Bidding 2009
Construction File: Pre-qualification Contributes to the Rising Cost of Construction
Construction File: Publicly Funded Building Projects - Standard Stipulated Price Contract Documents Updated
Construction File: Use of Standard Documents Reduces Risks
Construction File: Use of Standard Documents Reduces Risks
Construction File: CCDC issues new CCDC2 Stipulated Price Contract
Construction File: Risks to Owners of In House Construction When Projects are Over Budget
Construction File: A Guide to Standards & Practices in the Construction Industry
Construction File: BC Government Introduces Capital Procurement Audit Tool for Capital Asset Management Framework
Construction File: The Importance of Planholder List
Construction File: BCCA to Issue Onerous Bidding Alerts
Construction File: Myths of Gold Seal Requirements as a Condition of Contract
Construction File: Completion of Projects - Getting the Deficiencies Done!
Construction File: Why The Public Construction Council of BC?
Construction File: Procuring Trade Contractor Bids
Construction File: Pre-qualification of General Contractors and Trade Contractors
Construction File: Pre-qualification of General Contractors and Trade Contractors
Construction File: Maximizing Competitive Bidding
Construction File: Construction Management - Selection of CM and Contractor Services
Construction File: A Summary Guide for BC Construction Industry Standards and Guidelines
Construction File: BCCA Policy Gold Seal as a Condition of Contract
Construction File: BCCA POLICY FOR THRESHOLDS FOR PROCUREMENT OF PUBLICLY FUNDED CONSTRUCTION
Construction File: A Guide to the Use of Cash Allowances
Alternative Prices – Should They Be Used and How to Use Them Effectively
Publicly Funded Building Projects - Standard Stipulated Price Contract Documents Now Available Online
Construction File: Keeping Projects on Budget and Over Budget Negotiations
Construction File: COOLNet meets the requirements of AIT
Construction File: HOW DO YOU FIND THE RIGHT TRADE CONTRACTORS FOR YOUR PROJECT?
Construction File: Addressing Holdbacks
Construction File: Dangers of Owner-Supplied Equipment
Construction File: Standard Documents Provide Good Value
![construction-file-default.jpg](/media/400x300/construction-file-default.jpg)