Construction File: Construction Management - Selection of CM and Contractor Services
This information is not intended to assess the use of Construction Management but is offered as guidance to making the selection process for these services fair, open and transparent as possible. The BCCA policy for the use of Construction Management can be found on-line at http://bccassn.xpr.cloud/pdfs/cmguidelines2.pdf.
Regardless of whether the AIT applies or not, sole source selection of Construction Management services without a competitive process of some kind is not an open and transparent process for publicly funded projects. A pure qualification based selection process for Construction Management services, which does not take price into account at all, is also questionably a fair process.
The selection decision should be based strictly on the criteria and methodology set out in the RFP. No additional subjective factors that were not disclosed to the proponents should be considered. The evaluation should be performed by an evaluation team comprised of at least three people. It may also be desirable to have an independent fairness monitor to evaluate the entire process to ensure that no bias has played a part in the selection process. The use of an independent fairness monitor is a process that has been used by the Ministry of Transportation in British Columbia, when they are selecting the successful proponent in a subjective analysis environment.
Once a Construction Manager has been chosen, a clear and transparent process should also be followed in contracting with trade contractors (an independent fairness monitor should also be considered during this process). This should include the following:
- Any pre-qualification of trade contractors be completed based on objective evaluation of criteria.
- The use of Bid Depository.
- A local public tender opening.
- When the Construction Manager is bidding own forces to compete with the trade contractors for any trade packages, that are put out for bidding, then it must be clearly identified during the bidding process that the CM is a competitor. A transparent process for evaluation and selection of the successful contractor are imperative.
- The recommended use of standard contract CCA #17: Stipulated Price Contract for Trade Contractors on Construction Management Projects.
- All separate/alternate prices that are acceptable for consideration should be documented in the specifications or addenda.
- For the tender to be considered valid, it should be submitted as per plans specifications and addenda with no qualifications on the face of the tender.
- The awarding of contracts should be based on the lowest base bid or, if specified in the bid documents, on the lowest combination of base bid and acceptable alternative prices. Unsolicited alternatives should not be considered in the contract award.
.jpg)
.jpg)
Receiving Bids Efficiently in the 21st Century
.jpg)
Construction File: BCCA’s position on the BC NDP's Community Benefits Agreement
.jpg)
Construction File: What the New National Trade Agreements Mean to You
.jpg)
Construction File: Introducing the BCCA Guideline to Construction Close-Out Procedures
.jpg)
Construction File: Pre-qualification of Contractors

Construction File: Proactive Release of Project Information for the Construction Industry

Construction File: The Construction Management Project Delivery Method

Construction File: Public Openings for Online Bidding

Construction File: CCA Quality of Documents Report Issued

Construction File: Onerous Bidding Conditions in 2015

Construction File: Top 10 Reasons BidCentral’s Online Bidding is a Home Run

Construction File: Job Order Contracting

Construction File: Liquidated Damages Clauses

Construction File: The Importance of Planholder Lists

Construction File: Post Closing Over Budget Negotiations

Construction File: The Pitfalls of Incomplete Contract Documents

Construction File: BidCentral - By the Industry for the Industry

Construction File: What is Fair, Open and Transparent Bidding?

Construction File: Trade Contractors in Post Bid Negotiations and Trade Agreements

Construction File: Prompt Payment Creates a Sustainable Industry

Construction File: Fair Markups on Changes to the Work

Construction File: Tercon Decision Important for Construction Industry

Construction File: BCDC Standard Documents and Guidelines for a Stipulated Price Bid

Construction File: BidCentral implements new e-bonding

Construction File: Aboriginal Business Enhancement and Set-Aside Programs

Construction File: Liquidated Damages Clause

Construction File: BCCA Introduces a Guideline for Choosing a Project Delivery Method

Construction File: BCCA’s External Policy for Use of Owner Forces on Public Funded

Construction File: Onerous Bidding Conditions Continue to Trouble Industry

Construction File: Outsourcing = Best Value

Construction File: The Importance of Providing Bid Results
Construction File: Tercon Decision Important for Construction Industry
Construction File: Trade Contractors in Post Bid Negotiations and Trade Agreements
Construction File: The Cost of Onerous Bidding Conditions
Construction File: BCCA introduces the Electronic Bidding System
Construction File: Liquidated Damages Clause
Construction File: Maximizing Competitive Bidding 2009
Construction File: Pre-qualification Contributes to the Rising Cost of Construction
Construction File: Publicly Funded Building Projects - Standard Stipulated Price Contract Documents Updated
Construction File: Use of Standard Documents Reduces Risks
Construction File: Use of Standard Documents Reduces Risks
Construction File: CCDC issues new CCDC2 Stipulated Price Contract
Construction File: Risks to Owners of In House Construction When Projects are Over Budget
Construction File: A Guide to Standards & Practices in the Construction Industry
Construction File: BC Government Introduces Capital Procurement Audit Tool for Capital Asset Management Framework
Construction File: The Importance of Planholder List
Construction File: BCCA to Issue Onerous Bidding Alerts
Construction File: Myths of Gold Seal Requirements as a Condition of Contract
Construction File: Completion of Projects - Getting the Deficiencies Done!
Construction File: Why The Public Construction Council of BC?
Construction File: Procuring Trade Contractor Bids
Construction File: Pre-qualification of General Contractors and Trade Contractors
Construction File: Pre-qualification of General Contractors and Trade Contractors
Construction File: Maximizing Competitive Bidding
Construction File: Construction Management - Selection of CM and Contractor Services
Construction File: A Summary Guide for BC Construction Industry Standards and Guidelines
Construction File: BCCA Policy Gold Seal as a Condition of Contract
Construction File: BCCA POLICY FOR THRESHOLDS FOR PROCUREMENT OF PUBLICLY FUNDED CONSTRUCTION
Construction File: A Guide to the Use of Cash Allowances
Alternative Prices – Should They Be Used and How to Use Them Effectively
Publicly Funded Building Projects - Standard Stipulated Price Contract Documents Now Available Online
Construction File: Keeping Projects on Budget and Over Budget Negotiations
Construction File: COOLNet meets the requirements of AIT
Construction File: HOW DO YOU FIND THE RIGHT TRADE CONTRACTORS FOR YOUR PROJECT?
Construction File: Addressing Holdbacks
Construction File: Dangers of Owner-Supplied Equipment
Construction File: Standard Documents Provide Good Value