Construction File: Addressing Holdbacks
The most common reasons for withholding funds on a construction project are as follows: There may be a statutory requirement for a holdback, as is the case under the Builders Lien Act, or there may be a contractual agreement to hold back funds, generally in the event of deficiencies in the work. While both reasons are legitimate on their face, abuses can happen.
Some public owners may try to rely on the statutory holdbacks despite the fact that the applicable legislation does not apply. Others may impose unreasonable contractual obligations on the contractor and withhold funds for purposes other than simple deficiencies in an effort to warranty the work or guard against possible problems in the future. While public owners may take such an approach thinking it will ultimately protect their interests, it actually can result in an inequitable and unstable construction pyramid.
The payment schedule is critically important in the progress of a construction project. Any disruption or inequity in this process can upset the timely completion of the project, not only by causing disputes, but also by complicating the movement of funds down the construction chain. It is important, therefore, for public owners to evaluate their current policies on withholding funds and ensure that those policies are reasonable and appropriate.
In determining what is a reasonable withholding of funds on a construction project, public owners should look to standard industry procedures. The BC Construction Association has developed a policy for holdbacks that reflects the position of the Canadian construction industry. We encourage public owners to adopt the following policies in managing their construction projects.
Deficiencies: Where there are deficiencies, the consultant should provide the contractor with a complete and concise list to enable completion by a mutually accepted date. Funds held back for deficiencies should be based on the value of the outstanding work and should not exceed two times said value.
Builders Lien: The requirements of the Builders Lien Act should be complied with in all applicable circumstances. No funds should be withheld on projects where lien rights do not exist. Making use of standard industry policies and procedures on public construction results in quality construction!
The Construction File is a publication of the BC Construction Association.
For additional information contact the BCCA.
.jpg)
.jpg)
Receiving Bids Efficiently in the 21st Century
.jpg)
Construction File: BCCA’s position on the BC NDP's Community Benefits Agreement
.jpg)
Construction File: What the New National Trade Agreements Mean to You
.jpg)
Construction File: Introducing the BCCA Guideline to Construction Close-Out Procedures
.jpg)
Construction File: Pre-qualification of Contractors

Construction File: Proactive Release of Project Information for the Construction Industry

Construction File: The Construction Management Project Delivery Method

Construction File: Public Openings for Online Bidding

Construction File: CCA Quality of Documents Report Issued

Construction File: Onerous Bidding Conditions in 2015

Construction File: Top 10 Reasons BidCentral’s Online Bidding is a Home Run

Construction File: Job Order Contracting

Construction File: Liquidated Damages Clauses

Construction File: The Importance of Planholder Lists

Construction File: Post Closing Over Budget Negotiations

Construction File: The Pitfalls of Incomplete Contract Documents

Construction File: BidCentral - By the Industry for the Industry

Construction File: What is Fair, Open and Transparent Bidding?

Construction File: Trade Contractors in Post Bid Negotiations and Trade Agreements

Construction File: Prompt Payment Creates a Sustainable Industry

Construction File: Fair Markups on Changes to the Work

Construction File: Tercon Decision Important for Construction Industry

Construction File: BCDC Standard Documents and Guidelines for a Stipulated Price Bid

Construction File: BidCentral implements new e-bonding

Construction File: Aboriginal Business Enhancement and Set-Aside Programs

Construction File: Liquidated Damages Clause

Construction File: BCCA Introduces a Guideline for Choosing a Project Delivery Method

Construction File: BCCA’s External Policy for Use of Owner Forces on Public Funded

Construction File: Onerous Bidding Conditions Continue to Trouble Industry

Construction File: Outsourcing = Best Value

Construction File: The Importance of Providing Bid Results
Construction File: Tercon Decision Important for Construction Industry
Construction File: Trade Contractors in Post Bid Negotiations and Trade Agreements
Construction File: The Cost of Onerous Bidding Conditions
Construction File: BCCA introduces the Electronic Bidding System
Construction File: Liquidated Damages Clause
Construction File: Maximizing Competitive Bidding 2009
Construction File: Pre-qualification Contributes to the Rising Cost of Construction
Construction File: Publicly Funded Building Projects - Standard Stipulated Price Contract Documents Updated
Construction File: Use of Standard Documents Reduces Risks
Construction File: Use of Standard Documents Reduces Risks
Construction File: CCDC issues new CCDC2 Stipulated Price Contract
Construction File: Risks to Owners of In House Construction When Projects are Over Budget
Construction File: A Guide to Standards & Practices in the Construction Industry
Construction File: BC Government Introduces Capital Procurement Audit Tool for Capital Asset Management Framework
Construction File: The Importance of Planholder List
Construction File: BCCA to Issue Onerous Bidding Alerts
Construction File: Myths of Gold Seal Requirements as a Condition of Contract
Construction File: Completion of Projects - Getting the Deficiencies Done!
Construction File: Why The Public Construction Council of BC?
Construction File: Procuring Trade Contractor Bids
Construction File: Pre-qualification of General Contractors and Trade Contractors
Construction File: Pre-qualification of General Contractors and Trade Contractors
Construction File: Maximizing Competitive Bidding
Construction File: Construction Management - Selection of CM and Contractor Services
Construction File: A Summary Guide for BC Construction Industry Standards and Guidelines
Construction File: BCCA Policy Gold Seal as a Condition of Contract
Construction File: BCCA POLICY FOR THRESHOLDS FOR PROCUREMENT OF PUBLICLY FUNDED CONSTRUCTION
Construction File: A Guide to the Use of Cash Allowances
Alternative Prices – Should They Be Used and How to Use Them Effectively
Publicly Funded Building Projects - Standard Stipulated Price Contract Documents Now Available Online
Construction File: Keeping Projects on Budget and Over Budget Negotiations
Construction File: COOLNet meets the requirements of AIT
Construction File: HOW DO YOU FIND THE RIGHT TRADE CONTRACTORS FOR YOUR PROJECT?
Construction File: Addressing Holdbacks
Construction File: Dangers of Owner-Supplied Equipment
Construction File: Standard Documents Provide Good Value