.jpg)
Construction File: Liquidated Damages Clause
A liquidated damages clause will be enforceable where it represents a genuine pre-estimate of the damages an owner will likely suffer as a result of a contractor’s delay. However, where a liquidated damages clause is excessive and objectively unreasonable, it will likely be considered a penalty clause and will be unenforceable.
The courts in British Columbia have recognized that in some instances a breach of contract can give rise to damages which are difficult, costly and time consuming to prove and that it may be appropriate in these circumstances to utilize a liquidated damages clause. Following this approach, some owners have inserted detailed liquidated damages clauses into their tender and contract documents. These types of liquidated damages clauses tend to be drafted for the specific project in question and provide a formula for determining what the quantum of the liquidated damages may be. In so doing, the contractor knows its potential exposure in advance and may bid the project accordingly.
Other owners insert the same liquidated damages clause into most or all of their tender documents and contracts without having regard to the specific project being built. These liquidated damages clauses typically provide that the owner may deduct a specified amount (i.e. $500) per day for each day that the contractor fails to meet the agreed-upon completion date and also deduct all “out-of-pocket” costs incurred by the owner as a result of the delay. Notwithstanding the express terms of these types of liquidated damages clauses, it is likely that the specified per-day dollar amount is not a genuine pre-estimate of damages as it bears no relation to the construction issues surrounding the project. Further reference to undefined “out-of-pocket” costs makes determining and pricing potential exposure extremely difficult.
Other owners are moving away from liquidated damages clauses towards a damages recovery model not based on an express formula or even a specified per-day deduction; but rather, based on the concept of payment by the contractor of an amount equal to all costs and damages incurred by the owner as a result of the failure of the contractor to complete its work by the agreed upon completion date.
Over time, the courts have imposed limitations on what can be recovered by an owner as a result of delay(s) caused by a contractor. Courts generally restrict contractual damages to those which are directly caused by the breach of contract, or which were a reasonably foreseeable consequence of a breach of the specific contract in issue at the time the contract was entered into. In the face of these recovery rules, some owners insert clauses into tender documents and contracts designed to circumvent common law by giving notice to the contractor that damages that may not be recoverable under normal contractual principles are recoverable if the contractor is late in completing its work (e.g. indirect, consequential and incidental damages). These types of clauses give contractors no reasonable basis upon which to price the risk of late completion as there is no limit placed on what the owner can claim and potentially recover.
The insertion of liquidated damages and similar clauses in tender documents and contracts can increase bid prices and, depending on the precision in which they are drafted, may add price uncertainty. This may lead to inflated bid and contract prices which will not benefit an owner and may lead to a windfall for a contractor if there is no delay. Accordingly, before using a liquidated damages or similar clause, owners should seriously consider their overall benefit in the context of the construction project being built and, where damages may be difficult, costly and time consuming to prove, provide contractors with a precise mechanism for determining and pricing the risk.
BCCA wishes to acknowledgement Jenkins Marzban Logan for this article.
.jpg)
.jpg)
Receiving Bids Efficiently in the 21st Century
.jpg)
Construction File: BCCA’s position on the BC NDP's Community Benefits Agreement
.jpg)
Construction File: What the New National Trade Agreements Mean to You
.jpg)
Construction File: Introducing the BCCA Guideline to Construction Close-Out Procedures
.jpg)
Construction File: Pre-qualification of Contractors

Construction File: Proactive Release of Project Information for the Construction Industry

Construction File: The Construction Management Project Delivery Method

Construction File: Public Openings for Online Bidding

Construction File: CCA Quality of Documents Report Issued

Construction File: Onerous Bidding Conditions in 2015

Construction File: Top 10 Reasons BidCentral’s Online Bidding is a Home Run

Construction File: Job Order Contracting

Construction File: Liquidated Damages Clauses

Construction File: The Importance of Planholder Lists

Construction File: Post Closing Over Budget Negotiations

Construction File: The Pitfalls of Incomplete Contract Documents

Construction File: BidCentral - By the Industry for the Industry

Construction File: What is Fair, Open and Transparent Bidding?

Construction File: Trade Contractors in Post Bid Negotiations and Trade Agreements

Construction File: Prompt Payment Creates a Sustainable Industry

Construction File: Fair Markups on Changes to the Work

Construction File: Tercon Decision Important for Construction Industry

Construction File: BCDC Standard Documents and Guidelines for a Stipulated Price Bid

Construction File: BidCentral implements new e-bonding

Construction File: Aboriginal Business Enhancement and Set-Aside Programs

Construction File: Liquidated Damages Clause

Construction File: BCCA Introduces a Guideline for Choosing a Project Delivery Method

Construction File: BCCA’s External Policy for Use of Owner Forces on Public Funded

Construction File: Onerous Bidding Conditions Continue to Trouble Industry

Construction File: Outsourcing = Best Value

Construction File: The Importance of Providing Bid Results
Construction File: Tercon Decision Important for Construction Industry
Construction File: Trade Contractors in Post Bid Negotiations and Trade Agreements
Construction File: The Cost of Onerous Bidding Conditions
Construction File: BCCA introduces the Electronic Bidding System
Construction File: Liquidated Damages Clause
Construction File: Maximizing Competitive Bidding 2009
Construction File: Pre-qualification Contributes to the Rising Cost of Construction
Construction File: Publicly Funded Building Projects - Standard Stipulated Price Contract Documents Updated
Construction File: Use of Standard Documents Reduces Risks
Construction File: Use of Standard Documents Reduces Risks
Construction File: CCDC issues new CCDC2 Stipulated Price Contract
Construction File: Risks to Owners of In House Construction When Projects are Over Budget
Construction File: A Guide to Standards & Practices in the Construction Industry
Construction File: BC Government Introduces Capital Procurement Audit Tool for Capital Asset Management Framework
Construction File: The Importance of Planholder List
Construction File: BCCA to Issue Onerous Bidding Alerts
Construction File: Myths of Gold Seal Requirements as a Condition of Contract
Construction File: Completion of Projects - Getting the Deficiencies Done!
Construction File: Why The Public Construction Council of BC?
Construction File: Procuring Trade Contractor Bids
Construction File: Pre-qualification of General Contractors and Trade Contractors
Construction File: Pre-qualification of General Contractors and Trade Contractors
Construction File: Maximizing Competitive Bidding
Construction File: Construction Management - Selection of CM and Contractor Services
Construction File: A Summary Guide for BC Construction Industry Standards and Guidelines
Construction File: BCCA Policy Gold Seal as a Condition of Contract
Construction File: BCCA POLICY FOR THRESHOLDS FOR PROCUREMENT OF PUBLICLY FUNDED CONSTRUCTION
Construction File: A Guide to the Use of Cash Allowances
Alternative Prices – Should They Be Used and How to Use Them Effectively
Publicly Funded Building Projects - Standard Stipulated Price Contract Documents Now Available Online
Construction File: Keeping Projects on Budget and Over Budget Negotiations
Construction File: COOLNet meets the requirements of AIT
Construction File: HOW DO YOU FIND THE RIGHT TRADE CONTRACTORS FOR YOUR PROJECT?
Construction File: Addressing Holdbacks
Construction File: Dangers of Owner-Supplied Equipment
Construction File: Standard Documents Provide Good Value
