Construction File: Dangers of Owner-Supplied Equipment
A disturbing trend is emerging in public construction. Increasingly, owners are making the decision to supply their own equipment and material for construction projects. While at first glance there may appear to be economical advantages to the owner, the reality is, in most cases, the risks and the costs as- sociated that decision far outweigh the bene- fits.
In some instances it may be a sensible decision for an owner to furnish items that would normally fall to the contractor to provide. There may be a legitimate and clear price advantage or there may be a tight construction schedule and a long lead-time needed for the purchase of items. Prior to making the decision to supply equipment or materials, however, the owner should consider the potential problems that could arise.
For example, what are the consequences of late delivery? If the project does not proceed on schedule there will clearly be costs to the owner. Contractors are experienced at purchasing construction equipment and mate- rial. They are cognizant of the necessary delivery schedules, degree of assembly, installation needs and other physical requirements of a project. In choosing to supply his or her own material, the owner overlooks that valuable expertise. Instead, the owner is faced with additional responsibilities and liabilities.
What if materials are defective? If the owner supplies the material, they also take on this risk. When materials show up damaged or go missing the cost of rectifying the problems and the effect this may have on scheduling fall squarely on the shoulders of the owner.
As for achieving a cost benefit, the owner needs to be careful of unintended consequences. A contractor’s markup is more likely to increase when purchasing requirements are minimal, as this becomes the only avenue for achieving a profit. A contractor stays competitive by using his purchasing power for multiple projects. He or she is able to obtain lower prices thanks to the greater volume of product being purchased. Also, owners should factor in the costs of establishing and managing a purchasing department, servicing equipment and storing materials, all costs that would otherwise be carried by the contractor.
Owner-furnished equipment and materials have a very high potential for causing claim situations. Late deliveries, defects, and non-compliance with the contract requirements can delay and disrupt the project which in turn will lead to claims for the costs of corrective or additional work and schedule extensions. It only takes one serious claim to quickly evaporate any savings achieved.
We recommend that owners consider carefully their option to supply equipment and material on a construction project and that they use that option only in special circumstances such as when long delivery times are anticipated.
The Construction File is a publication of the BC Construction Association.
For additional information contact the BCCA.
.jpg)
.jpg)
Receiving Bids Efficiently in the 21st Century
.jpg)
Construction File: BCCA’s position on the BC NDP's Community Benefits Agreement
.jpg)
Construction File: What the New National Trade Agreements Mean to You
.jpg)
Construction File: Introducing the BCCA Guideline to Construction Close-Out Procedures
.jpg)
Construction File: Pre-qualification of Contractors

Construction File: Proactive Release of Project Information for the Construction Industry

Construction File: The Construction Management Project Delivery Method

Construction File: Public Openings for Online Bidding

Construction File: CCA Quality of Documents Report Issued

Construction File: Onerous Bidding Conditions in 2015

Construction File: Top 10 Reasons BidCentral’s Online Bidding is a Home Run

Construction File: Job Order Contracting

Construction File: Liquidated Damages Clauses

Construction File: The Importance of Planholder Lists

Construction File: Post Closing Over Budget Negotiations

Construction File: The Pitfalls of Incomplete Contract Documents

Construction File: BidCentral - By the Industry for the Industry

Construction File: What is Fair, Open and Transparent Bidding?

Construction File: Trade Contractors in Post Bid Negotiations and Trade Agreements

Construction File: Prompt Payment Creates a Sustainable Industry

Construction File: Fair Markups on Changes to the Work

Construction File: Tercon Decision Important for Construction Industry

Construction File: BCDC Standard Documents and Guidelines for a Stipulated Price Bid

Construction File: BidCentral implements new e-bonding

Construction File: Aboriginal Business Enhancement and Set-Aside Programs

Construction File: Liquidated Damages Clause

Construction File: BCCA Introduces a Guideline for Choosing a Project Delivery Method

Construction File: BCCA’s External Policy for Use of Owner Forces on Public Funded

Construction File: Onerous Bidding Conditions Continue to Trouble Industry

Construction File: Outsourcing = Best Value

Construction File: The Importance of Providing Bid Results
Construction File: Tercon Decision Important for Construction Industry
Construction File: Trade Contractors in Post Bid Negotiations and Trade Agreements
Construction File: The Cost of Onerous Bidding Conditions
Construction File: BCCA introduces the Electronic Bidding System
Construction File: Liquidated Damages Clause
Construction File: Maximizing Competitive Bidding 2009
Construction File: Pre-qualification Contributes to the Rising Cost of Construction
Construction File: Publicly Funded Building Projects - Standard Stipulated Price Contract Documents Updated
Construction File: Use of Standard Documents Reduces Risks
Construction File: Use of Standard Documents Reduces Risks
Construction File: CCDC issues new CCDC2 Stipulated Price Contract
Construction File: Risks to Owners of In House Construction When Projects are Over Budget
Construction File: A Guide to Standards & Practices in the Construction Industry
Construction File: BC Government Introduces Capital Procurement Audit Tool for Capital Asset Management Framework
Construction File: The Importance of Planholder List
Construction File: BCCA to Issue Onerous Bidding Alerts
Construction File: Myths of Gold Seal Requirements as a Condition of Contract
Construction File: Completion of Projects - Getting the Deficiencies Done!
Construction File: Why The Public Construction Council of BC?
Construction File: Procuring Trade Contractor Bids
Construction File: Pre-qualification of General Contractors and Trade Contractors
Construction File: Pre-qualification of General Contractors and Trade Contractors
Construction File: Maximizing Competitive Bidding
Construction File: Construction Management - Selection of CM and Contractor Services
Construction File: A Summary Guide for BC Construction Industry Standards and Guidelines
Construction File: BCCA Policy Gold Seal as a Condition of Contract
Construction File: BCCA POLICY FOR THRESHOLDS FOR PROCUREMENT OF PUBLICLY FUNDED CONSTRUCTION
Construction File: A Guide to the Use of Cash Allowances
Alternative Prices – Should They Be Used and How to Use Them Effectively
Publicly Funded Building Projects - Standard Stipulated Price Contract Documents Now Available Online
Construction File: Keeping Projects on Budget and Over Budget Negotiations
Construction File: COOLNet meets the requirements of AIT
Construction File: HOW DO YOU FIND THE RIGHT TRADE CONTRACTORS FOR YOUR PROJECT?
Construction File: Addressing Holdbacks
Construction File: Dangers of Owner-Supplied Equipment
Construction File: Standard Documents Provide Good Value