Construction File: Post Closing Over Budget Negotiations

The rationale of the tender process is to replace negotiation with competition and, subject to the terms of the tender documents, negotiation is generally not permitted in the tender process.  One of the primary reasons why negotiation is not permitted is to prevent bid shopping.  Generally, where the tender documents expressly permit negotiation, negotiation is only permissible so long as it is consistent with what is expressly provided in the tender documents.

It is not uncommon for owners to include a provision permitting negotiation with the lowest compliant bidder where all compliant bids received by an owner are over budget.  There are, however, potential (unintended) consequences that should be considered when including negotiation clauses in tender documents and in proceeding with post-closing over budget negotiations.

The tender process between an owner and general contractors typically comes to an end when one of the following events occurs:

(a) all bids are rejected;

(b) when one bid is accepted and the construction contract is entered into; or

(c) when the period of irrevocability expires. 

The conclusion of the tender process between the owner and general contractor also has the result of releasing the carried subcontractors from an obligation to enter into construction contracts with the general contractor.  Accordingly, and subject to the terms of tender documents, if the owner rejects all tenders submitted by general contractors as being over budget, the owner is generally free to negotiate with a general contractor if there was no improper purpose for the rejection and the procedures to bring about an end to the tender process were not abused.  If this occurs, the general contractor’s obligations to all subcontractors who submitted compliant tenders, including the carried subcontractors, are terminated, as are any obligations owed by the subcontractors to the general contractor. 

If, however, the owner does not specifically reject all general contractor bids but enters into a course of negotiations with a general contractor after the close of tenders and in accordance with the terms of the tender documents, an issue that may arise is whether the owner has complied with the tender documents and, in the circumstances, whether general contractor remains bound to enter into the construction contract with the carried subcontractor based on those negotiations.

If the negotiations between the owner and general contractor are properly characterized as a request by the owner, and an agreement by the owner, to the modification of a general contractor’s tender (within the clause in the tender documents permitting negotiation), the general contractor’s tender would continue in effect, as amended, and would not result in the release of the general contractor’s obligation to enter into construction contracts with the carried subcontractors, and vice versa.  However, if the negotiations are properly characterized as a rejection by the owner of the general contractor’s tender and the making by the owner of a counter-offer to the general contractor (outside the ambit of the negotiation clause), the tender process would have been terminated, along with the general contractor’s obligation to enter into construction contracts with the carried subcontractor, and vice versa.  This could be an unintended consequence of the negotiations between owner and general contractor.

Public owners face additional issues regarding over budget negotiations and a potential cancellation of a tender process as they must also be cognizant of what potential impacts post-close negotiations may have on their obligations under relevant trade agreements, including the New West Partnership Trade Agreement. 

Some industry organizations have issued best practices guidelines in response to the challenges posed by post-close over budget negotiations.  These are, however, guidelines and, by their nature, are not rules of law and the courts will always examine the substance of the negotiations between the owner and general contractor in order to determine what actually happened.

The Canadian Construction Document Committee has published a process for post-tender negotiations between owner and general contractor where all tenders submitted are over budget (see: CCDC 23 – 2005 A Guide to Calling Bids and Awarding Contracts).  Pursuant to this process, where the amount by which the bid price must be reduced by less than 15% of the lowest compliant bid, the first step is to negotiate with only the lowest compliant bidder in order to identify changes in the scope or quality of the work and the corresponding bid price reduction(s).  Where agreement is reached, it should be documented as a post-bid addendum and the contract, based on the negotiated reduced price, should be awarded.  Negotiations should be limited exclusively to the lowest complaint bidder.  Where agreement cannot be reached, the second step is to invite only the three lowest compliant bidders to re-tender on modified tender documents under a new invitation.  Where the amount by which the bid price must be reduced exceeds 15% of the lowest complaint bid, the owner may immediately undertake either of the preceding steps, at its discretion.  As recommended in this Guide, re-bidding should be avoided whenever possible because of the time and costs incurred by all parties. Where a re-bid is unavoidable, the Bid Documents should be sufficiently modified to achieve a reduced bid price acceptable to the Owner.

The British Columbia Construction Association and the Public Construction Council of British Columbia have a similar guide which discusses the propriety of post-tender negotiations see:Procedures and Guidelines Recommended for Use on Publicly-Funded Construction Projects).  It provides that the owner may negotiate changes with the lowest compliant general contractor as long as the negotiations are with that bidder only and between that bidder and its carried subcontractors only.  Further, if the negotiations do not produce a price acceptable to the owner, or if negotiations are impractical, all tenders should be rejected, the tender documents revised and a new tender called.  Critical to this process is that the general contractor can only negotiate with the subcontractors it carried in its tender to the owner. 

If negotiation is authorized by the tender documents, bid shopping during that process must be avoided.  Bid shopping encompasses conduct where a bid is used as a negotiating tool, whether expressly or in a more clandestine way, before the construction contract has been awarded and with a view to obtaining a better price or other contractual advantage.  For example, the disclosure of a contractor’s or subcontractor’s price to a competitor during post-close negotiations will be viewed as creating a sham tender process and attract the sanction of the courts.  Further, the entering into negotiations by the owner with the lowest compliant general contractor can lead to the shopping of subcontractors’ bids.  Accordingly, the owner should consider putting in place a proper process for general contractor / subcontractor negotiations in its tender documents.  For example, the BC Documents Committee expressly provides in its bid documents that owner has the right to enter into over-budget negotiations with the lowest compliant bidder, without cancellation of all bids or consideration to other bidders, and to require that bidder to negotiate with subcontractors named on their Bid Form (see: BCDC 2 – 2013 Standard Documents and Guidelines for a Stipulated Price Bid for use on Publicly Funded Building Projects).

In conclusion, terms permitting post close negotiation in over budget situations should be drafted with care and specifically with attention to the maintenance of the integrity of the tender process.  Any negotiations that take place based on an express negotiation provision must be followed.  The potential exists for unintended consequences through negotiation during the tender process, which can be avoided through properly drafted negotiation clauses and properly conducted over-budget negotiations.

Above information provided by Jenkins Marzban Logan LLP.

BCCA Comments:

Notwithstanding the information as outlined above BCCA believes there are other considerations in over budget negotiations:

  1. Trade Contractors and Suppliers play a significant role in projects often completing a substantial amount of the work. Ensuring they are treated fairly in over-budget negotiations is important. If a bid process is cancelled rather than including language in the Instructions to Bidders to allow negotiation, then there is likely no contract obligation to the Trade Contractors and Suppliers, which potentially creates opportunities for bid shopping.
  2. Under the New West Partnership Trade Agreement (NWPTA), if a bidding process is cancelled the post-close negotiations may be considered a new bid process where the owner is then subject to a new public bid process. As such that post-close negotiation may be considered as single sourcing, giving rise to a formal complaint under the new bid-dispute process that comes into effect July 1, 2015. To ensure NWPTA compliance we would recommend including language in the Instructions to Bidders which accommodates post bid closing over-budget negotiation. 
construction-file-default.jpg
December 22, 2015

Construction File: Onerous Bidding Conditions in 2015

The soon-to-be-published ‘Building a BC Construction Innovation Strategy’ (a joint initiative of BCCA and the Home Owner Protection Office) points out one of the biggest hindrances to innovation and productivity in the construction industry: the inequitable allocation of risk down the supply chain to those least able to support it.
Read More
construction-file-default.jpg
July 20, 2015

Construction File: Job Order Contracting

To support public owners in their efforts to hold themselves accountable to taxpayers through fair open, and transparent procurement practises, the BCCA offers Thresholds for Procurement of Publicly Funded Construction policy.
Read More
construction-file-default.jpg
July 20, 2015

Construction File: Liquidated Damages Clauses

By their very nature, liquidated damages clauses in contracts cause an adversarial relationship to exist from the outset on a construction project. Such clauses are used in contracts to assign financial responsibility to the contractor for damages that are likely to be incurred by the owner if the specified schedule is not met.
Read More
construction-file-default.jpg
May 15, 2015

Construction File: The Importance of Planholder Lists

Providing Planholder Lists to members is a core service provided for decades by the Construction Associations all across Canada. For example the Construction Association of Victoria, which started in 1912 as a Builders Exchange, is the oldest Construction Association west of Winnipeg and it has likely collected Planholders Lists almost from the very beginning of its 95 year existence.
Read More
construction-file-default.jpg
May 08, 2015

Construction File: Post Closing Over Budget Negotiations

The rationale of the tender process is to replace negotiation with competition and, subject to the terms of the tender documents, negotiation is generally not permitted in the tender process. One of the primary reasons why negotiation is not permitted is to prevent bid shopping. Generally, where the tender documents expressly permit negotiation, negotiation is only permissible so long as it is consistent with what is expressly provided in the tender documents.
Read More
construction-file-default.jpg
March 01, 2015

Construction File: The Pitfalls of Incomplete Contract Documents

In providing a price, contractors expect that the contract documents are complete and reflect the project requirements, and that any changes, errors or omissions from the documents will lead to a change order with commensurate adjustment to both the contract price and duration. As the bidding is done in a competitive environment, contractors and their subcontractors are reluctant to add allowances to their tendered price, fearing that they will not be successful as low bidder.
Read More
construction-file-default.jpg
February 01, 2015

Construction File: BidCentral - By the Industry for the Industry

Since the early days of Building Exchanges, facilitating and managing public construction bids has been a focal point for construction associations. The BC Construction Association (BCCA) and its regional construction association partners BCCA North, Southern Interior Construction Association, BCCA Vancouver Island and Vancouver Regional Construction Association, are no exception to this rule.
Read More
construction-file-default.jpg
June 17, 2014

Construction File: Prompt Payment Creates a Sustainable Industry

Construction work is project based, with unique project teams assembled through a tendering process. These project teams typically involve an owner who is the buyer of construction services from a general contractor, who in turn employs sub-contractors and often sub-sub-contractors. Add numerous suppliers to the mix, at all levels of the contracting pyramid.
Read More
construction-file-default.jpg
January 30, 2014

Construction File: Fair Markups on Changes to the Work

The impact of changes in the scope of work – both time and money – is probably the single most disputed issue in construction. Therefore, in order to keep the project moving toward completion, the contractual provisions governing changes must be fair as well as effective in encouraging the timely resolution of cost and time issues. However, feedback from contractors is that change order markups are a major issue. Two decades ago, the discussion about markups on changes to the work was not as intense as it is today. What has changed?
Read More
construction-file-default.jpg
August 20, 2013

Construction File: BidCentral implements new e-bonding

When the British Columbia Construction Association (BCCA) introduced online bidding three years ago – in the form of the BidCentral platform – there was one element of the process anticipated to go through the most significant evolution: the protocol for the submission of bid bonds online. Or, as it has now commonly become known: e-bonding.
Read More
construction-file-default.jpg
April 18, 2013

Construction File: Aboriginal Business Enhancement and Set-Aside Programs

With little to no exception, all levels of government within Canada have an aspiration to further economic development through their purchasing conduct – often highlighting specific populations and objectives. In addition to established policies, public sector entities continue to learn and expand policy and processes to do with minority groups such as Aboriginal suppliers. Recent examples in our province can be drawn from tenders for civil construction projects where preference is given to contractors who hire Aboriginal workers or who engage in Joint Venture with Aboriginal companies.
Read More
construction-file-default.jpg
January 03, 2013

Construction File: Liquidated Damages Clause

A liquidated damages clause will be enforceable where it represents a genuine pre-estimate of the damages an owner will likely suffer as a result of a contractor’s delay. However, where a liquidated damages clause is excessive and objectively unreasonable, it will likely be considered a penalty clause and will be unenforceable.
Read More
construction-file-default.jpg
February 13, 2012

Construction File: Onerous Bidding Conditions Continue to Trouble Industry

In our January 2007 Construction File we published how we were going to be issuing Contractor Alerts to bring attention to the onerous clauses that contractors see as an impediment to bidding on projects. In the five years since we introduced this protocol we have issued several Contractor Alerts. On the projects where it has been used it has been effective in educating contractors of the risks of onerous bidding conditions.
Read More
construction-file-default.jpg
December 08, 2010

Construction File: Outsourcing = Best Value

Government agencies in BC are facing increasingly tight budgets and the need to efficiently allocate scarce resources is critical. In order that the taxpayers can receive the best possible services, agencies must focus on their core activities and seek to outsource others to private industry.
Read More
April 01, 2010

Construction File: Tercon Decision Important for Construction Industry

“Egregious behaviour”. Behaviour seen as “an affront to the integrity and business efficacy of the tendering process”. So said the Supreme Court of Canada in its reasons for judgment in the recent Tercon Contractors Ltd. Appeal. They were referring to the actions of the BC Ministry of Transportation and Highways, during the tendering phase of a public construction project.
Read More
March 01, 2010

Construction File: Trade Contractors in Post Bid Negotiations and Trade Agreements

The prospect of a major construction job generally initiates a cascade of invitations to bid from the owner, to general contractors, to subcontractors, to suppliers and other participants. The invitations generate a corresponding flow of bids upwards along the same food chain. Each compliant bid submitted along that food chain creates a bid contract between the party seeking bids and the bidder which, generates corresponding obligations as expressly and impliedly set out in the bid documents.
Read More
December 21, 2009

Construction File: The Cost of Onerous Bidding Conditions

In the June 2002 BCCA Bulletin we published an article called ‘A Fine Day to be a Lawyer’. At that time we expressed concerns about the implementation of the BC Government’s Capital Asset Management Framework and in particular the removal of the BC Government’s Standard Stipulated Sum contract, which was removed under the guise of reducing red tape.
Read More
September 14, 2009

Construction File: BCCA introduces the Electronic Bidding System

The BCCA Electronic Bidding System is one component of the on-line bidding tools that were developed by BCCA along with Infinite Source Systems. What has been built is a seamless system that has the capability to eventually include everyone in the bidding chain from material suppliers bidding to subsubcontractors through to the general contractors bidding to owners.
Read More
May 06, 2009

Construction File: Liquidated Damages Clause

By their very nature, liquidated damages clauses in contracts cause an adversarial relationship to exist from the outset on a construction project. Such clauses are used in contracts to assign financial responsibility to the contractor for damages that are likely to be incurred by the owner if the specified schedule is not met.
Read More
September 10, 2008

Construction File: Pre-qualification Contributes to the Rising Cost of Construction

Why is it that BCCA is adamantly opposed to pre-qualification of contractors as general practice? In a nut shell, it is because of the subjectivity of the process. As a general practice we don’t see that it can be completely fair, open and transparent. Somewhere in the methodology, a decision is made that affects a contractor’s right to do business with the government based on some subjective consideration.
Read More
April 16, 2008

Construction File: Use of Standard Documents Reduces Risks

When documents contain clauses that discourage contractors from bidding, raise the costs associated with bidding, add onerous risk, or limit the competition to a select few bidders, it may come at a cost to the owner. Such an outcome creates the potential for unfairness or misuse of public funds.
Read More
April 15, 2008

Construction File: Use of Standard Documents Reduces Risks

When documents contain clauses that discourage contractors from bidding, raise the costs associated with bidding, add onerous risk, or limit the competition to a select few bidders, it may come at a cost to the owner. Such an outcome creates the potential for unfairness or misuse of public funds.
Read More
March 21, 2007

Construction File: The Importance of Planholder List

Providing Planholder Lists to members is a core service provided for decades by the Construction Associations all across Canada. For example the Construction Association of Victoria, which started in 1912 as a Builders Exchange, is the oldest Construction Association west of Winnipeg and it has likely collected Planholders Lists almost from the very beginning of its 95 year existence.
Read More
January 02, 2007

Construction File: BCCA to Issue Onerous Bidding Alerts

In an effort to advise contractors of the risks associated with onerous clauses in bidding documents, the BC Construction Association will be issuing Contractor Alerts. The Alerts are intended to bring attention to the onerous clauses that some contractors see as an impediment to bidding on projects.
Read More
November 30, 2006

Construction File: Myths of Gold Seal Requirements as a Condition of Contract

Recently there have been public owners who have implemented requirements for certification for Site Superintendents as a condition of contract on construction projects. The certification has been the CCA Gold Seal certification with the alternative requirement that the Site Superintendent be indentured in the Gold Seal program within a specified time period, after award of contract.
Read More
July 17, 2006

Construction File: Why The Public Construction Council of BC?

The Public Construction Council of BC has just begun its fourth decade in existence. It has not survived this many years without having good reason for its continued existence. One of the mandates of the Council is to maintain guidelines which promote open, fair and transparent bidding.
Read More
May 19, 2006

Construction File: Procuring Trade Contractor Bids

There has been a lot of discussion regarding the positive amount of construction on the books and being planned for British Columbia over the next few years. One area of concern that we hear from many stakeholders in the industry is where we are going to find the trade contractors with people to build our facilities and infrastructure.
Read More
January 11, 2006

Construction File: Maximizing Competitive Bidding

Given the environment for bidding in these busy times, we believe that owners are competing with each other for the strained resources of the industry. To attract contractors to bid your project and to ensure you are maximizing the competition, we recommend the following...
Read More
January 01, 2005

Construction File: A Guide to the Use of Cash Allowances

Cash allowances are recommended where it is impossible to clearly define the scope of a particular item of work, where it is difficult for bidders to accurately estimate the cost of a particular item of work or where access to certain building systems may limit the bidding competition.
Read More
October 01, 2003

Construction File: Addressing Holdbacks

The most common reasons for withholding funds on a construction project are as follows: There may be a statutory requirement for a holdback, as is the case under the Builders Lien Act, or there may be a contractual agreement to holdback funds, generally in the event of deficiencies in the work.
Read More